NHPC Limited Q4 profit rises 52% in Q4 to ₹919 crore; FY25 profit slips 15%

6 hours ago 1
Chairman and Managing Director, NHPC Ltd. ABL Srivastava addresses a press conference. File

Chairman and Managing Director, NHPC Ltd. ABL Srivastava addresses a press conference. File | Photo Credit: PTI

State-owned hydropower developer National Hydroelectric Power Corporation Private Limited (NHPC) has reported a 52% growth in its consolidated net profit to ₹919.63 crore for the March quarter, driven by increased income.

It posted a net profit of ₹605 crore in the January-March period of the preceding 2023-24 fiscal year, the company said in an exchange filing on Tuesday (May 20, 2025).

NHPC increased its income to ₹2,672.11 crore, from ₹2,320.18 crore in the same quarter a year ago.

However, for the entire FY25, the net profit declined by around 15% to ₹3,411.73 crore, from ₹3,999.54 crore in FY24.

The company’s board has recommended a final dividend of ₹0.51 per equity share of face value ₹10 for the financial year 2024–25, subject to shareholders’ approval at the upcoming Annual General Meeting.

This is in addition to the interim dividend of ₹1.40 per equity share for the FY 2024-25 paid in March 2025.

In April, the company commissioned the 800 MW Parbati-11 HE Project (hydroelectric) and 107.14 MW (out of a total of 300 MW) Karnisar Solar Power Plant. NHPC said that in October 2023, they were certain losses to the assets and consequential generation loss in Teesla-V, Teesta Low Dam-Ill & Teesta Low Dam-IV Power Stations owing to a flash flood in river Teesta.

Subsequently, in August 2024, another incident of landslide with certain consequential losses occurred at Teesta-V Power Station.

These losses are covered under Mega Insurance Policy and claims in this regard have been filed with the Insurance Company.

Accordingly, 'Other Income' for the quarter and financial year ended March 31, 2025 amounting to ₹44.34 crore and ₹108.59 crore, respectively, and 'Other Expenses' amounting to ₹28.66 crore and ₹99.73 crore for the quarter and financial year ended March 3 1, 2025, respectively, have been recognised in respect of 'Material Damage'.

Further, income on account of realisation of loss due to Business Interruption amounting to ₹ 111.52 crore and ₹409.02 crore has been recognised in 'Other Income' during the quarter and financial year ended March 31, 2025, respectively, on the basis of confirmation received from Insurance Company.

NHPC, under the Ministry of Power, is the largest hydropower development organisation in India, with capabilities to undertake all the activities from conceptualisation to commissioning of hydro projects.

Published - May 21, 2025 12:22 pm IST

Read Entire Article